Time Cost CPM scheduling analysis table

| July 16, 2015

Question 16: Time-Cost CPM Scheduling Model Analysis

 

Below are the data for a Time-Cost CPM Scheduling model analysis. The time is in days.

 

Activity Immediate Predecessor Normal Time Crash Time Normal Cost Crash Cost
A None 4 3 $213 $397
B A 4 3 $307 $623
C A 1 1 $212 $212
D B and C 5 4 $503 $551
E D 4 3 $494 $897

 

Part b: 4 points

 

What are the total normal cost of this project? Please give your answer in $.
Locally stored answer:

 

Part c: 6 points

 

If you crash this project to reduce the total time by one day (keeping the cost as low as possible), what is the total cost of the project? Please give your answer in $.
Locally stored answer:

 

Part d: 6 points

 

If you crash this project to reduce the total time by three days (keeping the cost as low as possible), what is the total cost of the project? Please give your answer in $.
Locally stored answer:

Get a 5 % discount on an order above $ 150
Use the following coupon code :
My2020Discount
Managing Ethics in Organizations
Organizational Theory and Behavior/ Other work

Category: Business

Our Services:
Order a customized paper today!