Project Management You must analyze each line in the WBS and list the activities necessary to complete each deliverable There are three levels in this WBS

Project Management You must analyze each line in the WBS and list the activities necessary to complete each deliverable There are three levels in this WBS; level 1: the project name, level 2: the summary tasks, level 3: the subtasks.  Every level needs to be expanded on by at least one subtask (except level 1). This means there will be, at most, four levels in this WBS. Level 2 summary tasks are common and will have well known subtasks so be on the look out for these activities we should think about what tasks/work needs to be done to meet the requirements we chose in the scope statement. 
Activities List with Duration Estimates and Resource Needs

ID#

Activity Name

Estimated Duration (in work hours)

Resource (person’s name or job title)

Predecessor (dependency)

 0

Recreation and Wellness Internet Project 

 

 

 

 1.0

Project Management

 

 

 

 2.0

Requirements Definition

 

 

 

 3.0

Web site design

 

 

 

 3.1

Registration for recreational programs

 

 

 

 3.2

Registration for classes and programs

 

 

 

 3.3

Tracking systems

 

 

 

 3.4

Incentive systems

 

 

 

 4.0

Web site development 

 

 

 

 4.1

Registration for recreational programs

 

 

 

 4.2

Registration for classes and programs

 

 

 

 4.3

Tracking systems

 

 

 

 4.4

Incentive systems

 

 

 

 5.0

Testing

 

 

 

 6.0

Training, rollout, and support

 

 

 

Example below,need to add subtask to 2.0,5.0,6.0

ID#

Activity Name

Estimated Duration (in work hours)

Resource (person’s name or job title)

Predecessor (dependency)

 0

Recreation and Wellness Internet Project 

 

 

 

 1.0

Project Management

 

 

 

    1.1

Integration

1.0

        1.1.1

Project Charter

1.1

    1.2

Scope

        1.1.2

Collect Requirements

1.1.1

        1.1.3

Scope Statement

1.1.2

WBS

    1.3

Schedule Management

          1.3.1

Develop Schedule

          1.3.2

Control Schedule

    1.4

Procurement 

1.1.3

          1.2.1

Plan Procurement management

1.2

          1.2.2

Kickoff-meeting(virtual)

1.2.1

          1.2.3

        ???

    1.3

Administration

          1.3.1

Project integration

          1.3.1

Task Assignment

2.0

Requirements Definition

 

 

 

    2.1

Software

    2.2

Educational Content

    2.3

    ???

3.0

Web site design

 120

 

2.0

     3.1

Registration for recreational programs

 

 

 

    3.1.1

Text

    3.1.2

Graphic Design

    3.1.3

Links

    3.2

Registration for classes and programs

 

 

 

    3.2.1

Text

    3.2.2

Graphic design

    3.2.3

Links 

3.3

Tracking systems

 

 

 

    3.3.1

Software Procurement 

    3.3

Software Deployment

    3.3

Configuration management

 3.4

Incentive systems

 

 

 

    3.4.1

Prize descriptions

4.0

Web site development 

 384

 Bobby

3.0

       4.1

Registration for recreational programs

 48

 Kim

3.1

    4.1.1

Coding/Scripting

48

Kim

3.1-3.3

 4.2

Registration for classes and programs

 48

 Ashok

3.2

4.2.1

Coding/Scripting

48

Ashok

3.2.1-3.2.3

 4.3

Tracking systems

 48

 Alfreda

3.3

    4.3.1

Database of contestants 

48

Alfreda

3.3.1

 4.4

Incentive systems

 48

 Kim

3.4

    4.4.1

Prizes for winners of contests

48

Alfreda

3.4.1

 5.0

Testing

 48

Entire Team

 4.4.1

5.1.1

Mock registration completed

12

Ashok

5.0

 6.0

Training, rollout, and support

 36

Entire Team

5.1.1 

6.1.1

Security policies 

12

Entire Team

6.0

6.1.2

Website published

12

Bobby

6.1.1